29/02/2020- Revamped homepage to make it cleaner and more user friendly.
1/03/2020- Started work on user manual and technical specification.
2/03/2020- Met with our supervisor today. Asked some questions about the marking breakdown so we could decide where to target our remaining work.
3/03/2020- Started designing our unit tests. Added time stamps to timeline feature.
4/03/2020- Performed some user tests with people involved in rugby. Also used the application to track a live game which exposed a glitch with the timestamps that was then quickly fixed.
5/03/2020- Filmed our video walk through and uploaded it to YouTube today. Also performed some more testing and added some finishing touches to the application.
6/03/2020- Final touches to technical spec and user manual today so we can add them to the git before the deadline. Uploaded everything to git and made sure everything was there.